QUESTION 11
In which order does Matrix Infrastructure Orchestration allocate storage pools?

image
Answer:

image
Explanation:
First – Static SAN volume automation
Second – Dynamic SAN volume automation
Third – Manual SAN Volume provisioning
Reference:
http://h20000.www2.hp.com/bc/docs/support/SupportManual/c03132773/c03132773.pdf (see page 125 and 126)

QUESTION 12
How is a template created for the Development department that specifies use of a dedicated LUN from a HP P2000 MSA for the VMware datastore?

A.    Hide all other storage devices in the IO Designer.
B.    Enable persistent building for the dedicated LUN
C.    Uncheck “Disk is shared across servers”
D.    Set a tag with the desired storage identifier

Answer: B

QUESTION 13
Which hypervisor platform requires a VLAN ID, when defining Network Pool resources in a CloudSystem Matrix “Create Network” tab?

A.    ESX vSphere
B.    Hyper-V
C.    KVM
D.    Integrity VM

Answer: B
Explanation:
http://h10032.www1.hp.com/ctg/Manual/c03326771.pdf (see page 64 and 65)

QUESTION 14
Match the file formats with the supported service template actions.

image

Answer:

image
Explanation:
PNG – Export only
VISIO – Export only
JPG – Export only
XML – Import only
Reference: http://h10032.www1.hp.com/ctg/Manual/c03326771.pdf (page 80, Importing and exporting templates)

QUESTION 15
Which command verifies that the Server Automation or Insight Control server deployment are configured in HP SIM?

A.    mxnodesecurity
B.    mxnode
C.    mxauth
D.    mxreport

Answer: B
Explanation:
http://h10018.www1.hp.com/wwsolutions/misc/hpsim-helpfiles/hpsim_userGuide.pdf (page 56, see mxnode)

QUESTION 16
In HPIO Designer, which additional processes can be added to a template besides the server, disks, and networks? (Select two)

A.    Fixed costs
B.    User accounts
C.    Workflow
D.    Scripts
E.    Performance requirements

Answer: AC

QUESTION 17
It is January and the Development department is working on a new application. They are using physical servers for their development environment. Management decides that the Development department should work on a problem in the current application for the next two months. They will use another service for troubleshooting. In April, they will start working on the new application again. What should the Development department do with the new application development service?

A.    Change the lease start date to April
B.    Reduce the lease to February and reactivate in April
C.    Extend the lease to a date past April
D.    Delete the service and recreate in April

Answer: B

QUESTION 18
An HP CloudSystem solution has been installed on the company data center to accommodate three (Dev, OA, Prod) departments computing requirements. Each department insists that they are the only owners who control and access their services, but the resource are shared using an IT as a service model with weekly pricing for services. Each group has their own Designer account and designed users are placed in the IO_users group. Some templates are shared all three departments.
The Dev department has decided to contribute six additional DL380 servers to the environment to be used as hypervisor hosts with the requirement that only they can have access to those servers.
The Prod department has encountered situations where their services are placed on low performance disk drives and has asked that the situations be fixed to use high performance drives.
The QA department utilization of the cloud is sporadic. When they use it, the QA department guidelines heavy loads during the entire week-long testing cycle.
Refer to the scenario. The QA department wants to have an account that can build templates for their own people to use, without needing to go through administrative processes to configure them. To provide this level of access, which windows user group does this account need to be added?

A.    HPIO_Diagonistics
B.    HPIO_Users
C.    HPIO_Architects
D.    HPIO_Administrators

Answer: C

QUESTION 19
An HP CloudSystem solution has been installed on the company data center to accommodate three (Dev, OA, Prod) departments computing requirements. Each department insists that they are the only owners who control and access their services, but the resource are shared using an IT as a service model with weekly pricing for services. Each group has their own Designer account and designed users are placed in the IO_users group. Some templates are shared all three departments.
The Dev department has decided to contribute six additional DL380 servers to the environment to be used as hypervisor hosts with the requirement that only they can have access to those servers.
The Prod department has encountered situations where their services are placed on low performance disk drives and has asked that the situations be fixed to use high performance drives.
The QA department utilization of the cloud is sporadic. When they use it, the QA department guidelines heavy loads during the entire week-long testing cycle.
Refer to the scenario.
Management has asked for a strategy moving forward that can address the disk performance issues that the Prod department is having. Which strategy can be implemented to give Prod the opportunity to ensure performance for their services, while encouraging other departments to evaluate their own requirements before ordering services?

A.    Add a Prod tag to all the high performance disks
B.    Alter which disk type each template is utilizing
C.    Remove other department tags from high performance
D.    Change the pricing scheme for disk space to include service tiers

Answer: B

QUESTION 20
An HP CloudSystem solution has been installed on the company data center to accommodate three (Dev, OA, Prod) departments computing requirements. Each department insists that they are the only owners who control and access their services, but the resource are shared using an IT as a service model with weekly pricing for services. Each group has their own Designer account and designed users are placed in the IO_users group. Some templates are shared all three departments.
The Dev department has decided to contribute six additional DL380 servers to the environment to
be used as hypervisor hosts with the requirement that only they can have access to those servers.
The Prod department has encountered situations where their services are placed on low performance disk drives and has asked that the situations be fixed to use high performance drives.
The QA department utilization of the cloud is sporadic. When they use it, the QA department guidelines heavy loads during the entire week-long testing cycle.
Refer to the scenario.
Which modification is needed to allow the additional Dev servers to be accessed once they have been assigned to the server pool?

A.    Modify users to add Dev department user accounts
B.    Remove all servers not part of the Dev department
C.    Modify users to add the IO_Users groups access
D.    Add the Dev department tag to the servers

Answer: A

If you want to pass HP HP0-D15 successfully, donot missing to read latest lead2pass HP HP0-D15 exam questions.
If you can master all lead2pass questions you will able to pass 100% guaranteed.

http://www.lead2pass.com/HP0-D15.html

Why Choose Lead2pass?

If you want to pass the exam successfully in first attempt you have to choose the best IT study material provider, in my opinion, Lead2pass is one of the best way to prepare for the exam.

Lead2pass Testking Pass4sure Actualtests Others
$99.99 $124.99 $125.99 $189 $29.99-$49.99
Up-to-Dated
Real Questions
Error Correction
Printable PDF
Premium VCE
VCE Simulator
One Time Purchase
Instant Download
Unlimited Install
100% Pass Guarantee
100% Money Back